Highlights of FSP
A total amount of Rs 1,778 Crore will be spent on the feeder separation project
funded by Rural Electrification Corporation and Asian Development Bank (ADB). The
project includes separation of 1645 no 11kV rural feeder of 17 districts benefiting
15860 villages.
|
|
------------------------------------------------------------------------------------------------------------------------------
|
|
Lot wise Status
Lot wise status in a dashbord format are available in this section.
|
|
-------------------------------------------------------------------------------------------------------------------------------
|
|
Targets for the Month
During the month, new feeders were to be surveyed & new BOQ's were to
be finalized.
Execution work is being carried out in divisions.
|
|
----------------------------------------------------------------------------------------------------------------------------------
|
|
Location of the Month
This section highlights location (lot no) with maximum progress as compared to other
locations, in a particlar month.
|
|
-----------------------------------------------------------------------------------------------------------------------------------
|
|
Site Photos
In this section, lot wise photographs of work at site will be uploaded by supervision
consultant.
|